Rylee's Ace Hardware the Helpful Place

Three Locations to Serve You:

click to shop at Ace
click to check you Rewards Points
Share on facebook

Blog Catagories

Subscribe to Our Feed

Register to Comment on Our Blog

We love to hear from our customers. This form allows you to become a registered user of the Rylee's website. As a registered user, you will be able to see additional content on our website and make comments on our blog.



Blog Archive

Snow Season

Are You Ready For The Snow? Rylee's Ace Hardware Is Fully Stocked For the Upcoming Snow Season Click to Learn More

#000000

Imagine It Organized

Got Clutter? Rylee's is having a class to get you organized. Click to Learn More

#000000

Ann Clark Cookie Cutters

Ann Clark cookie cutters are now available at Rylee's Ace on Michigan Street. Click to Learn More

#000000

Unique Housewares Department

You will find gifts in our housewares department that you can't find anywhere else. Click to Learn More

#000000
http://www.ryleesace.com/components/com_gk2_photoslide/images/thumbm/792618snowstorm.jpg
http://www.ryleesace.com/components/com_gk2_photoslide/images/thumbm/645729OrganizingSpecialists_logo_small.jpg
http://www.ryleesace.com/components/com_gk2_photoslide/images/thumbm/451701ann_clark.jpg
http://www.ryleesace.com/components/com_gk2_photoslide/images/thumbm/467800kitchen_gadgets2.jpg
thumbnailthumbnailthumbnailthumbnail
PDF Print E-mail

The Building Continues At Michigan Street

Progress Made This Week 10/5/09 thru 10/9/09

The masons have been working on the main entrance. All of the joists are set. Decking will be complete Monday. The Electrician has been installing the interior underground pipe. Excavator installed top soil at the parking lot islands. Masons have started washing block. Roof blocking was installed. Electrician installed temp lights and power to the building. Excavators have started to level the interior floor. HVAC curbs were installed. Roofing material has started to arrive.

Work to Begin Next Week 10/12 thru 10/16

Complete structural steel and decking. Complete masonry. Start Roofing. Coninue with interior grading. Install roof drains and pipe. Continue interior electrical underground. Install irrigation north of the parking lot and the islands. Start on under floor drains. Continue interior plumbing underground.

 